    违约赔偿合同在一些比较正式的合作当中经常用到,如果与国外有合作关系,一般合同是中译英对照版,以下就是世联北京翻译公司关于违约赔偿合同的翻译。
      (1)  Liquidated Damages
      译:违约赔偿
      (a) If any Local Contractor fails to meet the delivery time agreed in the relevant Local Contract, and subject to the provisions of such Local Contract or herein, the SD&AS Contractor shall, on behalf of the Owner, claim the (liquidated) damages from the Local Contractor, which shall be paid directly to the Owner or deducted by the Owner from any payment under the relevant Local Contract.
      译:如果任何本地承包方没有遵守相关本地合同中的交货时间,则根据该本地合同或本协议的规定,方案设计和相关服务承包方应代表业主方要求本地承包方支付违约赔偿金,应直接向业主方支付或由业主方根据相关本地合同尚未支付的合同价格中扣除。
      (b) If the total amount of delay liquidated damages payable by the SD&AS Contractor calculated on the rate set out in the sub-Clause 2.6.1 above exceeds the total amount of delay damages payable by the Local Contractors and the SD&AS Contractor (within the capacity of the contractor performing the Scheme Design Services) under the respective Local Contracts and the SD&AS Contract, the SD&AS Contractor’s sole liability to the Owner with respect to delay in achieving the Mechanical Completion shall be to pay, but subject to the limitation set forth in sub-Clause 2.6.1, such exceeding amount to the Owner.  SD&AS Contractor shall pay such amount to the Owner immediately after the SD&AS Contractor, acting on behalf of the Owner, has settled all the liquidated damages with all the liable Local Contractors.
      译:如果根据以上第2.6.1款规定方案设计和相关服务承包方应支付的延期违约赔偿金超过所有本地承包方和方案设计和相关服务承包方根据相关本地合同和方案设计和相关服务合同应支付的延期违约赔偿金总额(关于承包方履行方案设计服务),则方案设计和相关服务承包方由于未能按期实现基本竣工而向业主方承担的唯一责任是向业主方支付超过的差额。并适用于以上第2.6.1款规定的限制性条件。方案设计和相关服务承包方应在方案设计和相关服务承包方代表业主方与相关本地承包方结算违约赔偿金后立即向业主方支付以上差额。
      In sum, the Owner’s sole and exclusive remedy with respect to delay in achieving the Mechanical Completion is described in the following formula:
      译:从金额角度讲,业主方对于未能按期实现基本竣工的唯一排它责任通过以下公式表述:
      (1)-[(2)+(3)];但不能超过合同总价的4%。
      译:(i) - ; but not exceeding 4% of the Total Contract Price
      In the above formula:
      译:在以上公式中:
      (i) means the total amount of delay liquidated damages payable by the SD&AS Contractor calculated on the rate set out in the sub-Clause 2.6.1;
      译:指方案设计和相关服务承包方根据第2.6.1款规定应支付的延期违约赔偿金总额;
      (ii) means the total amount of damages (whether liquidated or not) payable by the Local Contractors under the respective Local Contracts; and
      译:指本地承包方根据相关本地合同应支付的赔偿金总额(不论是否为违约赔偿金);以及
      (iii) means the amount of damages payable by the SD&AS Contractor (within the capacity of the contractor performing the SD Services) under the SD&AS Contract.
      译:指方案设计和相关服务承包方(在承包方履行方案设计服务时)根据方案设计和相关服务合同应支付的赔偿金。